A Critical Analysis of Causes and Effects of Delays in Nigeria's National Integrated Power Projects (NIPP)

Main Article Content

Samuel O. F Onah

Abstract

This study critically analyzes the causes and effects of delays in Nigeria's National Integrated Power Projects (NIPP), focusing on the factors contributing to time overruns and their impact on project delivery. Utilizing a descriptive quantitative research design, primary data were collected through questionnaires and interviews with professionals involved in NIPP projects, while secondary data was sourced from relevant literature. The study identifies key delay factors, including political interference, poor feasibility studies, payment delays, and consultant inefficiencies, using the Relative Importance Index (RII) method. The findings reveal that client-related and consultant-related factors significantly contribute to delays, exacerbating Nigeria’s ongoing power crisis and hindering economic growth. Policy recommendations include improving project governance, strengthening planning processes, streamlining financial management, and enhancing stakeholder collaboration. These measures aim to address the root causes of delays and ensure timely completion of future infrastructure projects, supporting sustainable national development.

Article Details

How to Cite
Onah, S. O. F. (2024). A Critical Analysis of Causes and Effects of Delays in Nigeria’s National Integrated Power Projects (NIPP) . African Economic and Management Review, 4(1), 22–29. https://doi.org/10.53790/aemr.v4i1.102
Section
Articles

References

Aibinu, A. and Jagboro, G. (2002) The Effects of Construction Delays on Project Delivery in Nigerian Construction Industry. International Journal of Project Management, 20, 593-599.

http://dx.doi.org/10.1016/S0263-7863(02)00028-5

El-Razek, M. E. A., Bassioni, H. A., & Mobarak, A. M. (2008). Causes of delay in building construction projects in Egypt. Journal of Construction Engineering and Management, 134(11), 831-841. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:11(831)

Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in developing countries: Ghana as a case study. International Journal of Project Management, 21(5), 321-326. https://doi.org/10.1016/S0263-7863(02)00055-8

Kaliba, C., Muya, M., & Mumba, K. (2009). Cost escalation and schedule delays in road construction projects in Zambia. International Journal of Project Management, 27(5), 522-531. https://doi.org/10.1016/j.ijproman.2008.07.003

Kelley, J. E., & ALKERt, M. R. W. (1959). Critical-path planning and scheduling. Com.Au. Retrieved August 25, 2024, from https://mosaicprojects.com.au/PDF/PM-History_Critical_Path_Planning_&_Scheduling_Kelley_and_Walker_1959.pdf

Mansfield, N. R., Ugwu, O. O., & Doran, T. (1994). Causes of delay and cost overruns in Nigerian construction projects. International Journal of Project Management, 12(4), 254-260. https://doi.org/10.1016/0263-7863(94)90050-7

Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996). Construction delays in a fast-growing economy: Comparing Thailand with other economies. International Journal of Project Management, 14(1), 37–45. https://doi.org/10.1016/0263-7863(95)00052-6

Omoregie, A., & Radford, D. (2006). Infrastructure delays and cost escalation: Causes and effects in Nigeria. Proceedings of the 6th International Postgraduate Research Conference in the Built and Human Environment, University of Salford, UK. Retrieved from https://repository.derby.ac.uk/item/94y57/infrastructure-delays-and-cost-escalation-causes-and-effects-in-nigeria

Oyewobi, L. O., Ibironke, O. T., Ganiyu, B. O., & Ola-Awo, A. W. (2011). Evaluating rework cost: A study of selected building projects in Niger State, Nigeria. Journal of Geography and Regional Planning, 4(3), 147-154. Retrieved from https://academicjournals.org/journal/JGRP/article-full-text-pdf/E5D50E040790

Sambasivan, M. and Soon, Y.W. (2007) Causes and Effects of Delays in Malaysian Construction Industry. International Journal of Project Management, 25, 517-526.

https://doi.org/10.1016/j.ijproman.2006.11.007

Shrestha, B. K. (2021). Relationship between Standardization Critical Success Factors (CSFs) and Project Performance. ProQuest Dissertations Publishing. Retrieved from https://digitalscholarship.unlv.edu/cgi/viewcontent.cgi?article=5269&context=thesesdissertations

Sovacool, B. K., Gilbert, A., & Nugent, D. (2014). Risk, innovation, electricity infrastructure and construction cost overruns: Testing six hypotheses. Energy (Oxford, England), 74, 906–917. https://doi.org/10.1016/j.energy.2014.07.070

Von Bertalanffy, L. (1968). General System Theory Foundations, Development. New York George Braziller. - References - Scientific Research Publishing. (n.d.). Scirp.Org. Retrieved August 25, 2024, from https://www.scirp.org/reference/referencespapers?referenceid=2040488